Construction Laydown Site Preparation
As part of the Wastewater Treatment Project, the contractor Harbour Resource Partners and its subcontractors will begin to construct laydown area at 327 Anson Street for the McLoughlin Point Wastewater Treatment Plant. The work includes:
- Construction of temporary laydown area
- Construction of a chain-link perimeter fence
Work Description:
- Earthworks equipment will be used to supply and install gravel to construct the laydown area
- Temporary construction fencing will surround perimeter of work area
- Signage will be posted prior to work
Traffic Impacts:
- No street closures will be required
- On average 25 trucks per day (roundtrips) will be bringing equipment and materials to and from the site at 327 Anson Street
Start Date: Week of May 29th
Work Hours: 7:00 a.m. to 7:00 p.m. Monday to Friday
Location: 327 Anson St.